

Systematic was contracted to remove existing emergency hog conveyor and replace with a new chain conveyor. The main challenge of the project was overall access and space surrounding the conveyor. This project required the new conveyor to be threaded through an exterior wall during the annual shutdown. This rebuild was completed with approximately 1.5 weeks with the main demolition occurring during plant operations.
Role in Provisions of Works and Services:
Systematic provided supply & install of pinning carriages for Loader and Unloader.
Role in Provisions of Works and Services:
Role in Provisions of Works and Services:
Installation of all:
Field Commissioning and start up support
Services provided: Rigging, welding, millwrighting, iron working, field technical services - Modify and repair frame
Systematic was involved in the demolition of a small DLI canter line and the installation of the new Comact DDM6 small log line.
Role in Provisions of Works and Services
Systematic was GC for project divisions excluding electrical, controls, and HVAC. Works and services included:
Role in Provisions of Works and Services:
Role in Provisions of Works and Services:
Systematic was contracted to provide labour for the relocation of an existing 4-Bin Sheet Stacker and installation of a new Elite Automation 2-Bin Random Stacker. The project required demolition of transfer trays, walkways and structural, relocation of the sheet stacker to a new location, air receiver and piping reconfiguration, hydraulic unit/hosing relocation, walkway installation and Elite Automation Random Stacker installation.
Shutdown/Installation
Demolition:
Installation
Sheet Stacker Relocation:
Elite Random Stacker Installation:
Role in Provisions of Works and Services
Systematic provided labour for rebuild of plywood press to allow for 6 more openings. Press components removed down to base; rebuild included new access steel for crown. New piping for thermal oil, hydraulics, and compressed air.
Role in Provisions of Works and Services:
Role in Provisions of Works and Services
Role in Provisions of Works and Services
Role in Provisions of Works and Services
Plywood Plant Venner Dryer and Stacker line
Relocation of lathe Line from McBride Forest Industries
Completing the veneer dryer and stacker line rebuild and relocation at Coastland’s Annacis Island operations in Delta, BC.
Removed and replaced plywood plant equipment at the new greenfield building in Kamloops.
Completed rebuild of Westfraser’s plywood plant veneer dryer and other essential equipment.
Systematic was responsible for the installation of a new veneer dryer at Louisiana-Pacific’s Golden operations.
Systematic completed a comprehensive Veneer Dryer Installation project, encompassing the installation of a state-of-the-art veneer dryer, a veneer grade, and a stacker line. Our experts meticulously commissioned the entire system, guaranteeing its seamless integration into Tolko’s Armstrong operations.
Systematic designed the layout and foundations for a new plywood press, completing construction on a 15 ft deep press pit and sheet pile perimeter. Additionally the team installed the new press and its associated in-feed and out-feed equipment.
Systematic was responsible for bringing new life to a used plywood press. This included redesigning the overall layout, applying alterations to the used press, and modifying the used in-feed/out-feed equipment and other associated elements. The final installation to ensure proper integration and functionality was also performed by our team.
Systematic was contracted to complete Liebherr replacement, ponds reconditioning and rails extension at West Fraser Grande Prairie OSB plant.
Role in Provisions of Works and Services:
Services provided: Rigging, welding, millwrighting, iron worker, field technical services and commissioning
Provided demolition, structural erection and mechanical assembly services for the new siding manufacturing project.
Assembly of the following:
New Building and Process Piping Installation:
An 11 day shutdown to replace an old A5 debarker with a new A8 debarker was executed.
Project Overview
Existing Debarker #2 Removal:
Modify and Repair Debarker Support Structure:
Role in Provisions of Works and Services:
Pre-shutdown installation of small log chipper infeed deck c/w concrete foundation structural steel, infeed deck chains and ancillary equipment.
Demolition of small and large debarker infeed decks, cut-off saw, structural steel and concrete foundations.
Structural erection and mechanical assembly of new infeed deck system.
Assembly of the following:
Process Piping Installation:
Services provided:
Rigging, welding, millwrighting, pipefitting, iron worker, field technical services and commissioning
Structural erection of equipment enclosure structural and envelope
Mechanical Installation
Services provided: Rigging, welding, millwrighting, iron working, field technical services and commissioning
Systematic was contracted to remove existing dryer and install a new MEC dryer. The removal and install required navigating a 62’long barrel drum through existing mill with minimal mill interruption. The path through mill consisted of a tight “S” turn, with approximately 8 inches of clearance. The project was completed while the surroundings dryers operated.
Role in Provisions of Works and Services:
14 MW Turbo Generator Installation:
Role in Provisions of Works and Services:
Role in Provisions of Works and Services
Systematic was responsible for dryer planning and layout design
Much of the dryer construction was completed prior to the surrounding building installation due to project constraints and overall design of building and dryer
Existing Demolition
New Installation
Systematic was contracted to remove existing dryers and install two new MEC dryers. The removal and install required navigating a 62' long barrel drum through an existing mill with minimal mill interruption. The path through the mill consisted of a tight "S" turn, with approximately 6 inches of clearance. The project was completed while the surrounding dryers operated.
Role in Provisions of Works and Services:
Systematic was contracted to remove existing dryer and install a new MEC dryer. The removal and install required navigating a 62' long barrel drum through existing mill with minimal mill interruption. The path through mill consisted of a tight "S" turn, with approximately 6 inches of clearance. The project was completed while the surrounding dryers operated. This was the final dryer to be replaced. Previously Systematic replaced 3/4 dryers (S23511, S23548).
Role in Provisions of Works and Services:
Systematic was contracted to remove jack ladder take away conveyors from an elevated platform and reinstall newly designed conveyors. This project took place during the annual shutdown of 7 days. All work was constructed on an elevated platform with minimal headroom. The surrounding structure dictated the install methodology.
Role in Provisions of Works and Services:
Completed all required modifications within a two day outage to allow for an upgrade of the fire supression of the main Super screen. Successfully replaced the legs and pannelling on the screen, as well as provided calibration and commissioning support.
Provided demolition, structural erection and mechanical assembly services for the new siding manufacturing project.
Assembly of the following:
New Building and Process Piping Installation:
Systematic’s industrial construction and trade contracting work ranges from mining and processing sites to the installation of complete plants, lines, and single machines.





























